Produkter
Download
Ekspertise
Service
Hvem er vi
Information
Bestil retur
Presse
Søg efter resultater (Ingen søgeresultater for )
You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.
Railway tunnel with subterranean stations, station expansion and entrance area
Design: the tunnel section is being built using the cut-and-cover method; the semi-monolithic method in the trough construction procedure
Internal width: up to 21.00 m
Internal height: 7.20 m to 9.85 m
NCC Construction Sverige AB (Malmö C Nedre, E101)
ARGE MCG Malmö Citytunnel (Entrance Area E201);
Bilfinger Berger AG, Per Aarsleff A/S, E. Pihl & Son A.S.
The bottom plate, walls and slabs could be constructed in 10-day cycles with the PERI tunnel formwork. PERI has always provided us with the best solution.
Combination consisting of project-specific formwork carriage constructions and rentable PERI system equipment: 2 formwork carriages for the casting segment in advance, two subsequent slab formwork carriages and a VARIO solution for the elliptical reinforced concrete columns along the tunnel centre. Additionally, two formwork carriages for the southern entrance area with two parallel tunnel constructions.